This document breaks down the 'overhead' areas
involved in building the kennels before work commences,
(eg: plant/machinery, labour, noise, security, admin, utilities, site meetings,
site access etc) to complete the project as shown on the blueprints.
Each area in the Preliminaries & Construction
Specification is to be given a 'cost' & included in
the Pricing Document (so you can see
an exact, like-for-like comparison between quotations)
|
This document is of most importance to kennel owners who are using a building
contractor.
However, if you are physically constructing the kennels yourself, or bringing
in specialist labour for certain elements, the need for this section is reduced.
Also helpful: see our Project Management
article (Members only) if you need help deciding whether to manage
the project yourself, or get an architect/ project manager.
Some of the areas the Preliminaries document covers:
-
Insurance - Does the contractor have full liability
insurance? Do you know what amount they should be covered for?
-
Access - do you need to provide a temporary
road to gain access to the area of development? If so, this needs to be highlighted
& a cost set against it.
-
Waste materials - what might need to be removed
& associated costs, which can be surprising!
-
PRELIMINARIES/ GENERAL CONDITIONS
-
TENDER INSTRUCTIONS:
- Type of Tender
- Inclusive Tender
- Items in Specification Not Priced
- Correction of Arithmetical Errors
- Pricing of Specification/ Schedule of Work
-
EMPLOYER’S REQUIREMENTS:
3.1 Management of the Works
- Definition of “Contractor”
- Insurances
- Master Programme
- Site Meetings
- Extensions of Time
3.2 Quality Standards/ Controls
- Material & Goods
- British Standards & Codes of Practice
- Good Practice
- Proprietary Articles & Specialist Firms
- Manufacturer’s Recommendations
- Approvals
3.3 Security/Safety/Protection
- Construction (Design & Management) Regulations 1994
- Noise & Pollution
- Maintain Public & Private Roads
- Maintain Live Services
- Security
- Protection of Work in All Sections
- Prevention of Damage
- Asbestos Materials
- Safety Fencing
- Entering or Leaving the Site
3.4 Specific Limitations on Method/ Sequence/ Timing
- Access
- Use of Site
- Start of Work
3.5 Facilities/Temporary Work/ Services
- Temporary Fences, Hoardings, Screens & Roofs
- Working Hours
-
CONTRACTOR’S GENERAL COST ITEMS:
- Management & Staff
- Site Accommodation
- Power
- Lighting
- Fuels
- Water
- Telephone & Administration
- Safety, Health & Welfare
- Storage of Materials
- Cleaning
- Drying Out
- Protection of Work in all Sections
- Small Plant & Tools
- Waste
- Disbursements Arising from the Employment of Work People & Purchases of
Materials & Goods
- Other Services & Goods
- Mechanical Plant
- Temporary Works